
A major hospitality organisation used the Agile DSDM framework to develop a sales and marketing system. The company had previously used Waterfall for all projects. DSDM was selected after a workshop on the pros and cons of Waterfall and Agile. The project had strong support from senior managers, business SMEs and technical specialists. A third-party company was responsible for the development.
Before starting the project, DSDM training was delivered to the project team. This approach was much more effective than training the team during the project. Everyone understood their role and the differences in activities compared to Waterfall projects.
The business had been considering the project for several months before it started and had a long list of features that they wanted to include. MoSCoW was used to prioritise them.
The senior stakeholders welcomed the benefits of the DSDM structure, especially the deliverables from the timebox approach. Seeing the priority features delivered instilled a high level of confidence in the project. Additionally, the approach alleviated initial concerns about the risk of going over budget. The core functionality was released on time and to budget. Additional features were added to the backlog, and they were included in subsequent phases.
The review concluded that the project provided the required business benefits and that the use of DSDM had been successful.
This was a complex transformation programme for a media company. The project involved replacing legacy editorial systems and the infrastructure. It highlights the importance of planning on an Agile project.
The project was managed using Agile with additional project management governance relating to the infrastructure transformation. The business processes were time critical, with process dependencies at each step. Each sprint had key features/deliverables that were mandatory for that phase.
Dress rehearsals were a key part of risk management. They highlighted 90 additional issues that were not discovered in testing, and 45 were resolved before go-live. One of the issues relating to the timing of a critical BAU process. The deadline for completing all BAU activities would have been missed on the first day of go-live. The error didn’t show up in UAT because of assumed timings. When the complete process was run end-to-end during a dress rehearsal, the issue was discovered. The matter was resolved, and there were no issues with the timings after go-live.
An organisation implemented a major transformation project that included new integrations with associated data mappings. The team was reluctant to document the data mappings or integrations because they were following Agile and quoted the Agile Manifesto every time the issue was raised.
The integrations took considerably longer than expected, with the resulting delay in cutover to the new system.
They were also reluctant to document the configuration for the support team and referred to the Manifesto again. The support team made their position very clear: ‘If you don’t deliver the information, how do you expect us to provide support?’
The key learnings for the organisation from this project were a deeper understanding of the Agile Manifesto and the importance of communicating with everyone involved in the project, especially the support team you are going to hand over to.
Note: When the manifesto refers to comprehensive documentation, many IT professionals believe this refers to the 300-page requirements documents that were common at one point on Waterfall projects. I think we’ll all agree that such documentation is not required on an Agile project, but it doesn’t mean that a project team doesn’t do any documentation.
Let’s start by dismissing one of the greatest misunderstandings of Agile; that it doesn’t include planning except for the current sprint. This is not correct, and people that argue otherwise probably haven’t worked on major Agile programmes.
If you have been involved in rescuing a failing Agile project, it’s not uncommon to hear statements like, ‘We are Agile; we don’t do planning,’ and ‘I haven’t prepared a roadmap; this isn’t a Waterfall project.’
Common issues with the lack of planning and preparation of a roadmap include:
Please note: Some regulators may not approve the use of any application developed using Agile. Scrum for Safety may be acceptable in some regulated environments, but ensure you have formal agreement from all stakeholders before deciding to use any Agile framework on a project subject to regulation.
There are a number of different approaches when estimating Agile projects. It is critical to remember that, on average, activities take over twice as long as expected. This was highlighted by a research project by a leading UK university. They reviewed actual time against estimates for a number of industries and found that people tend to underestimate both effort and elapsed time for activities. Please factor this into your plans.
One of the most frequent issues seen on failing projects is Agile not being used properly. Doing nothing more than holding a standup each morning does not mean that an organisation is following Agile methodology.
Regardless of methodology, agreeing on and tracking deliverables is key to managing a successful project. Whether it is the deliverable from a sprint in Agile or a milestone in a Waterfall project plan, stakeholders will require updates on progress. Understanding, tracking and managing dependencies between deliverables is essential.
In some Agile frameworks updating stakeholders isn’t a high priority, but it can be critical. Please consider this scenario:
It isn’t uncommon to hear that the only information available is the sprint completion dates, not the contents of the sprints. This isn’t correct and it may contribute to project failures. A sprint should contain features that will be delivered, and if a critical feature isn’t going to be included, the product owner should review this with the team, analyse the impact and update the relevant stakeholders.
On a project that had to be rescued, the team said that they were following Agile and the content of the delivery depended on the quality assurance process. Therefore, they could not confirm the deliverables until the day before the release. This was not acceptable to the senior stakeholders, and changes were made to provide advance notice and assurance of deliverables in each sprint.
On many programmes misunderstanding the Agile Manifesto and principles were major contributing factors that resulted in project rescue.
The Agile Manifesto was created in 2001. It describes the four principles of agile development:
Manifesto for Agile Software Development (agilemanifesto.org)
There’s an important point to consider. Many people misinterpret the principles in the Agile Manifesto, and this can have serious implications for projects. They mistakenly assume that the items on the right are not important (or don’t apply at all) on an Agile project, but their assumption isn’t correct.
The Agile Manifesto's principles prioritise the items on the left, but the ones on the right are still included. They are important, and the degree of importance depends on:
Another common comment is that plans aren’t used with Agile. A plan is recommended if you are working on a major transformation programme that involves:
This does not diminish the value of Agile on the programme, especially for the development, but an overall plan will usually be required to coordinate this level of activity.
The following 12 principles are based on the Agile Manifesto.
12 Principles Behind the Agile Manifesto | Agile Alliance
For best practice, please consider the following:
Please use the contact form below if you have any questions or would like to discuss any training, coaching or mentoring.
Copyright Pathway IT Consultants Limited 2025-2026
Pathway IT Consultants Registered Office: Mansion House, Manchester Road, Altrincham, Cheshire, WA14 4RW
Company Number 6200503
VAT Registration Number 975 9277 52
enquiries@pathwayitconsultants.co.uk
Training locations in Milton Keynes and throughout the UK.
Images have been created using JollyDeck Copilot AI or they are stock images.
Please Select Your Free Item

We specialise in training in the UK. Sorry, our free items are only available in the UK.